Rough shaping on tees has taken place on holes 4, 8 and 16. Shaping work will begin on 12 tee tomorrow with 14 tee beginning early next week. At this stage in the project, we will move all necessary material to where it is needed for each tee. Once this is complete on all holes, we will then come back to smooth and level to the final grade before grassing. We currently estimate tee construction to be complete by June 14th.
#16 Complete |
#7 Complete |
Jason mowing #2 for the first time. |
#9 after it's first mowing. |
#8 tee under construction. |
#16 tee under construction. |