Saturday, May 18, 2019

Project Update - May 18

The grounds department finished up another busy week working on both the project and the grounds. Things are taking shape and the new green slope/bunker complexes are nearing completion. This week was predominately consumed with sod installation. We accomplished the following:

  • Completed all sod installation on holes 2 and 9. This included approximately 60,000 sq.ft. of sod!
  • Began sod installation on hole 16 including completion of the paspalum around the green.
  • Completed bunker drainage installation on holes 7 and 16.
  • Began construction of the new tees on hole 4.
Next week we plan to complete all sod installation remaining on holes 16 and 7. We will also begin to increase focus on new tee complexes being renovated.

Monday started with the delivery of 16,000 square feet of sod in big rolls.


Installing rolls versus piece sod is a more efficient process requiring less labor.

#9 following sod installation.


#2 complete with paspalum sod around the green.

The exhausted crew putting the finishing touches on the paspalum around 16 green Friday night.