- Completed all sod installation on holes 2 and 9. This included approximately 60,000 sq.ft. of sod!
- Began sod installation on hole 16 including completion of the paspalum around the green.
- Completed bunker drainage installation on holes 7 and 16.
- Began construction of the new tees on hole 4.
Monday started with the delivery of 16,000 square feet of sod in big rolls. |
Installing rolls versus piece sod is a more efficient process requiring less labor. |
#9 following sod installation. |
#2 complete with paspalum sod around the green. |
The exhausted crew putting the finishing touches on the paspalum around 16 green Friday night. |