Thursday, August 30, 2018

Project Update - August 30

Early afternoon storms made today a little challenging. Progress slowed slightly but we were able to complete holes 6, 13 and 14 today. Work continued on hole 15 including the completion of new irrigation for the green. The severe storms prevented the installation of sod which will now begin on Friday.

I continue to remind you how hard our employees have worked throughout this project. The guys are tired but continue to push ahead, even in bad weather. If you have the chance, I encourage you to thank the employees for their efforts. 


Storms brought heavy rain this afternoon.


High winds were strong enough to snap this palm tree.


Cristino is a great example of our dedicated employees. Here he is after the storm standing up to his knees in water to get the job done.


No comments:

Post a Comment