The Isla Grounds Team finished clearing the old grass and began irrigation installation on #2 today. Shaping work on this hole will begin Wednesday.

Sod was removed from around #9 green slope today to prepare for shaping to take place later this week.


Arturo and Adam are cutting sod from around #9 green.



Yesterday, we removed grass behind the Red and Gold tees on #4. Today we were able to haul loose fill material to this area to practice with our laser grade box. This will help with efficiency when it comes time to level new tees.


Setting up and calibrating the laser grade equipment.



Tomorrow, the Red and Gold tees on #4 will be moved to temporary locations to allow for more sod removal around the forward tees. We will begin hauling material from #2 and #9 green slopes to #4 for the expansion of the forward tee space. Hauling this material directly to #4 from numbers 2 and 9 will save us from having to load and haul twice, resulting in greater efficiency. Stay tuned for more details on these new improvements!  