- Bunkers are constructed and drainage installed on holes 6 and 14.
- The sod installation on #14 is complete.
- Sod installation on holes 6 and 13 will be completed on Thursday.
- Work is underway on hole #15. The old grass has been removed.
- The old bunkers on #15 have been removed.
- A significant amount of grading has taken place on #15.
- New irrigation installation on #15 will be completed on Thursday.
- Sod installation will continue on #15 on Friday and will be complete early next week.
- The old grass has been cut and will be removed from the tee complex on hole #1 on Thursday.
- Additional soil will be hauled to the 1st tee throughout the remainder of the week.
- Shaping will take place on hole #1 throughout the weekend and into the first part of next week.
- Sod installation for the 1st tee is scheduled for next Thursday at which time the actual construction phase of our entire project will be complete except for bunker sand installation.
- Bunker sand installation is scheduled for the last week of September.

#6 Bunker and surrounds has been sodded. Installation will be completed on #6 on Thursday.

#14 sod installation is complete.

Work is underway on hole #15.

This photo shows where the front bunker used to be on #15 before being removed.
No comments:
Post a Comment